A simple description of what I would like to see is: please look at the attached image.
Legend:
- 2 weeks sprint
- different focus factors
- 0.8: all team members except D
- 0.6: team member D
- 5 members
Values on Estimated hours should be the result of 80 hours (or 60 hours) per sprint - days off (vacation, holiday, sick leave).
Values on Net capacity should be the above result multiplied with the focus factor.