Since upgrading to ScrumWorks Pro 4.3, we seem to be experiencing a problem retrieving Task estimates via the Java API
We are using ScrumWorksEndpoint.getTaskEstimates(TaskWSO task) to get the estimates. Previously, it returned an array of estimates, now we just get a single item with an estimate value of 0.
Please investigate and advise.
Thanks
Mike Brown
ProQuest
-
Hi Mike,
I will pass this along to the team.
Off the top of my head I would guess that this has to do with two specific changes:
# Tasks can be saved without an estimate. Task estimates are no longer required.
# Tasks "Done" Sprint Burndown chart. New overlay on the Sprint Burndown Chart tracks the burndown of finished tasks with blue points and lines.
I hope to have a reply for you soon. -